Hospital Construction Activity This Week

  

    


Building Care, also called Forest B, of Phase 2 of Children's Hospital expansion is underway and the new building is planned to open in Spring of 2022.
The 310,000 square-foot addition will add an eight-story building and will includes diagnostic and treatment facilities, primarily out-patient cancer and others) labs, new state-of-the-art operating rooms, 20 inpatient beds, and a lobby. There will be two floors of underground parking and sterile processing. This will bring SCH bed total to 409, up from 200 before its expansion 2012 plan.
The helicopter landing pad moved temporarily to the roof of Forest A (176’), now known as Friends of Costco Building, Phase 1 of the expansion. The landing pad will be active until Building Care is completed. Noise is expected to be louder than the former ground-based helipad. When Forest B is complete, the helistop will moves to its permanent location on top of the Friends of Costco Building (same height).
The Hospital posted this information on their Construction Blog about specific construction activity this week:
Major construction on Building Care will conclude in October, but work will continue within the building until spring 2022. After October, we will no longer publish weekly posts on the Construction Blog for Building Care. However, we will continue to post to this blog whenever an activity will affect neighbors.
  • Build out interior spaces on all levels
  • River Entrance vestibule renovations begin (pending carpenter availability); alternative entry into River 3 will be provided adjacent to the vestibule
All work will take place 8-6pm weekdays and 9-6pm on Saturdays.  
Call 206-987-8000 or email construction@seattlechildrens.org with questions.