Building Care, also called Forest B, of Phase 2 of Children's Hospital expansion is underway and the new building is planned to open in Spring of 2022.
The 310,000 square-foot addition will add an eight-story building and will includes diagnostic and treatment facilities, primarily out-patient cancer and others) labs, new state-of-the-art operating rooms, 20 inpatient beds, and a lobby. There will be two floors of underground parking and sterile processing. This will bring SCH bed total to 409, up from 200 before its expansion 2012 plan.
The helicopter landing pad moved temporarily to the roof of Forest A (176’), now known as Friends of Costco Building, Phase 1 of the expansion. The landing pad will be active until Building Care is completed. Noise is expected to be louder than the former ground-based helipad. When Forest B is complete, the helistop will moves to its permanent location on top of the Friends of Costco Building (same height).
Lights were added to the horizontal swing arm (boom) portion of the tower crane to increase safety for helicopter landings. These are in addition to the lights at the end of the boom and on the crane operator’s cab. The additional lights will help the helicopter pilots in identifying the location of the boom when landing or departing the helipad in the dark. While the lights are visible from the ground, they are not bright enough to interfere with any neighboring properties. As a reminder, the tower crane is scheduled to remain onsite through August 2020.
The Hospital posted this information on their Construction Blog about specific construction activity this week:
- 40th Avenue NE Pavement Restoration: Puget Sound Energy will restore the pavement within 40th Avenue NE between Seattle Children’s Emergency Department (ED) driveways and Sand Point Way NE. Work is expected to last about a week.
- Erect cladding and support steel
- Pour concrete for walls, shafts, slabs, pads, curbs and decks
- Install fireproofing
- Paint
- Install anchors and clips for windows
- Set and weld exterior walls
- Install roofing
- Set rooftop chillers
- Install glass
- Install elevator machines and equipment
- Install mechanical, electrical and plumbing equipment
- Install exterior sheeting
- Build out electrical, mechanical, generator and pneumatic tube blower rooms
- Install insulation
- Install fire sprinkler systems
- Install flooring
- Install exhaust air, plumbing and medical gas risers
- Interior activities: paint and clean on River B level 3 for new vending machines location; demolish walls and install mechanical, electrical and plumbing for new chapel location on River A level 7.
Work hours are 8-6pm weekdays and 9-6pm on Saturday.
For questions, call 206-987-8000 or email construction@seattlechildrens.org.