Monday, October 19, 2020

Hospital Crane To Be Removed This Week-End With Increased Noise 6am-6pm


Building Care, also called Forest B, of Phase 2 of Children's Hospital expansion is underway and the new building is planned to open in Spring of 2022.

This week-end the tower crane will be removed. The Hospital posted this information:
On Friday, a mobile crane will arrive at the site around noon in preparation for the removal. Expect increased noise and truck activity to and from the construction site.  We do not anticipate any impacts to street parking or traffic flow.
Sellen Construction has submitted a noise variance request to the City of Seattle, which would allow work to occur outside standard construction hours: Saturday and Sunday from 6am-6pm. 

The 310,000 square-foot addition will add an eight-story building and will includes diagnostic and treatment facilities, primarily out-patient cancer and others) labs, new state-of-the-art operating rooms, 20 inpatient beds, and a lobby. There will be two floors of underground parking and sterile processing. This will bring SCH bed total to 409, up from 200 before its expansion 2012 plan.

The helicopter landing pad moved temporarily to the roof of Forest A (176’), now known as Friends of Costco Building, Phase 1 of the expansion. The landing pad will be active until Building Care is completed. Noise is expected to be louder than the former ground-based helipad. When Forest B is complete, the helistop will moves to its permanent location on top of the Friends of Costco Building (same height).
Lights were added to the horizontal swing arm (boom) portion of the tower crane to increase safety for helicopter landings. These are in addition to the lights at the end of the boom and on the crane operator’s cab. The additional lights will help the helicopter pilots in identifying the location of the boom when landing or departing the helipad in the dark. While the lights are visible from the ground, they are not bright enough to interfere with any neighboring properties. As a reminder, the tower crane is scheduled to remain onsite through August 2020.
The Hospital posted this information on their Construction Blog about specific construction activity this week:
  • Dismantle and remove tower crane (see separate blog post called “Building Care Tower Crane to Be Removed” for details)
  • Pour concrete for slabs and walls
  • Framing
  • Paint
  • Install roofing
  • Install windows
  • Install elevator equipment
  • Install metal sheeting and panels
  • Install mechanical and electrical wiring and plumbing equipment
  • Install drywall
  • Install siding
  • Build out electrical, mechanical, telecommunication, machine and generator rooms
  • Install flooring
  • Build out interior spaces
  • Set air handling units
  • Building connection work:
    • Set up infection prevention barriers and demolish walls, ceilings, and windows on level 5 of River C
    • Install insulation and drywall on level 6 of River C
    • Form and pour concrete slab on level 7 of River C
    • Paint on level L1 of Forest A
    • Frame walls, set walls, and install utility wiring, steel beam, and fireproofing on level 1 of Forest A
    • Complete framing and install utility wiring and pneumatic tube connections on level 2 of Forest A
    • Set walls and install seismic joints and pneumatic tube connections on level 3 of Forest A
    • Set walls on level 4 of Forest A
    • Install seismic joint covers on level 5 of Forest A
    • Paint on level 6 of Forest A
    • Paint, patch ceiling, trim utility wiring, and install flooring on level 7 of Forest A
    • Trim utility wiring and install flooring on level 8 of Forest A
    • Paint, install drywall, and trim utility wiring on level 9 of Forest A

All work will take place 8-6pm weekdays and 9-6pm on Saturdays.
Call 206-987-8000 or email construction@seattlechildrens.org with questions.

No comments: