Wednesday, September 22, 2021

Hospital Construction Activity This Week


 

    


Building Care, also called Forest B, of Phase 2 of Children's Hospital expansion is underway and the new building is planned to open in Spring of 2022.
The 310,000 square-foot addition will add an eight-story building and will includes diagnostic and treatment facilities, primarily out-patient cancer and others) labs, new state-of-the-art operating rooms, 20 inpatient beds, and a lobby. There will be two floors of underground parking and sterile processing. This will bring SCH bed total to 409, up from 200 before its expansion 2012 plan.
The helicopter landing pad moved temporarily to the roof of Forest A (176’), now known as Friends of Costco Building, Phase 1 of the expansion. The landing pad will be active until Building Care is completed. Noise is expected to be louder than the former ground-based helipad. When Forest B is complete, the helistop will moves to its permanent location on top of the Friends of Costco Building (same height).
The Hospital posted this information on their Construction Blog about specific construction activity this week:
    • Restore sidewalks on Sand Point Way NE and 40th Avenue NE - place asphalt paving to restore the bike lane in an area between 40th Avenue NE and the hospital’s main entrance at Penny Drive. The paving will take one day. 

      This work was previously scheduled but was delayed by weather. The construction crew is expected to perform the paving this week, possibly as soon as Wednesday, Sept. 22.

    • Build out interior spaces
    • Remove temporary vestibule at River entrance
    • Install soil and mulch
    • Plant landscaping

All work will take place 8-6pm weekdays and 9-6pm on Saturdays.  
Call 206-987-8000 or email construction@seattlechildrens.org with questions.

No comments: