Building Care, also called Forest B, of Phase 2 of Children's Hospital expansion is underway and the new building is planned to open in Spring of 2022.
The 310,000 square-foot addition will add an eight-story building and will includes diagnostic and treatment facilities, primarily out-patient cancer and others) labs, new state-of-the-art operating rooms, 20 inpatient beds, and a lobby. There will be two floors of underground parking and sterile processing. This will bring SCH bed total to 409, up from 200 before its expansion 2012 plan.
The Hospital posted this information on their Construction Blog about specific construction activity this week:
- Soil amendment work around four trees in the southwest corner of campus (near the intersection of 40th Avenue NE and NE 45th Street). Crew will use air-pressurized equipment, which will produce some noise.
- Build out interior spaces
- Framing
- Paint
- Install roofing
- Install metal sheeting and panels
- Install mechanical and electrical wiring and plumbing equipment
- Install drywall
- Install elevator equipment
- Install ceilings
- Demolish hard surfaces in north parking lot
- Install flooring
- Building connection work:
- Paint and install ceiling and utility wiring on level 3 of River C
- Install ceilings on level 7 of River C
- Install steel and decking, and form and pour footings on level 1 of Forest A