Monday, November 30, 2020

Hospital Construction Activity This Week


 


Building Care, also called Forest B, of Phase 2 of Children's Hospital expansion is underway and the new building is planned to open in Spring of 2022.
The tower crane was recently removed. 
The 310,000 square-foot addition will add an eight-story building and will includes diagnostic and treatment facilities, primarily out-patient cancer and others) labs, new state-of-the-art operating rooms, 20 inpatient beds, and a lobby. There will be two floors of underground parking and sterile processing. This will bring SCH bed total to 409, up from 200 before its expansion 2012 plan.

The helicopter landing pad moved temporarily to the roof of Forest A (176’), now known as Friends of Costco Building, Phase 1 of the expansion. The landing pad will be active until Building Care is completed. Noise is expected to be louder than the former ground-based helipad. When Forest B is complete, the helistop will moves to its permanent location on top of the Friends of Costco Building (same height).
The Hospital posted this information on their Construction Blog about specific construction activity this week:
  • Framing
  • Paint
  • Install roofing
  • Install windows
  • Install ductwork
  • Install metal sheeting and panels
  • Install mechanical and electrical wiring and plumbing equipment
  • Install drywall
  • Waterproofing
  • Install siding
  • Install elevator equipment
  • Install ceilings
  • Build out electrical, mechanical, telecommunication, machine and generator rooms
  • Install flooring
  • Build out interior spaces
  • Install sprinkler system
  • Building connection work:
    • Demolish walls and ceiling and install utility wiring on level 3 of River C
    • Paint and install utility wiring and ceiling on level 5 of River C
    • Install expansion joint covers, utility wiring, and ceiling on level 6 of River C
    • Install expansion joint covers on level 7 of River C
    • Paint and install ceiling on level L1 of Forest A
    • Paint and install flooring on level 1 of Forest A
    • Remove infection prevention barriers on level 2 of Forest A
    • Paint, install corner guards, and remove infection prevention barriers on level 3 of Forest A
    • Paint and install ceiling, utility wiring, and corner guards on level 4 of Forest A
    • Paint and install ceiling and utility wiring on level 5 of Forest A

All work will take place 8-6pm weekdays and 9-6pm on Saturdays.
Call 206-987-8000 or email construction@seattlechildrens.org with questions.