The 310,000 square-foot addition will add an eight-story building and will includes diagnostic and treatment facilities, primarily out-patient cancer and others) labs, new state-of-the-art operating rooms, 20 inpatient beds, and a lobby. There will be two floors of underground parking and sterile processing. This will bring SCH bed total to 409, up from 200 before its expansion 2012 plan.
The helicopter landing pad moved temporarily to the roof of Forest A (176’), now known as Friends of Costco Building, Phase 1 of the expansion. The landing pad will be active until Building Care is completed. Noise is expected to be louder than the former ground-based helipad. When Forest B is complete, the helistop will moves to its permanent location on top of the Friends of Costco Building (same height).
Lights were added to the horizontal swing arm (boom) portion of the tower crane to increase safety for helicopter landings. These are in addition to the lights at the end of the boom and on the crane operator’s cab. The additional lights will help the helicopter pilots in identifying the location of the boom when landing or departing the helipad in the dark. While the lights are visible from the ground, they are not bright enough to interfere with any neighboring properties. As a reminder, the tower crane is scheduled to remain onsite through August 2020.
The Hospital posted this information on their Construction Blog about specific construction activity this week:
- Pour concrete for slabs and walls
- Install fireproofing
- Framing
- Paint
- Install roofing
- Set walls
- Install windows
- Install metal sheeting
- Install elevator equipment
- Install mechanical and electrical wiring and plumbing equipment
- Install drywall
- Install siding
- Build out electrical, mechanical, and generator rooms
- Install insulation
- Install flooring
- Install sprinkler systems
- Build out interior spaces
- Set air handling units
- Electrical power installation (Seattle City Light)
- Work in existing buildings:
- Complete installation of Starbucks kiosk on River B level 3
- Set up infection prevention barriers and demolish windows, walls, and ceilings on River C level 6
- Complete work on new chapel location on River A level 7
- Building connection work:
- Complete framing and install seismic joints, utility wiring, and insulation on level L1 of Forest A
- Set walls and install utility wiring and fireproofing on level 1 of Forest A
- Set walls on level 3 of Forest A
- Set walls and install seismic joints, utility wiring, and pneumatic tube connections on level 4 of Forest A
- Set walls, install utility wiring and pneumatic tube connections, and complete framing on level 5 of Forest A
- Complete framing and install utility wiring and insulation on level 6 of Forest A
- Install drywall, seismic joint covers, and insulation on level 7 of Forest A
- Paint, patch ceilings, and trim utility wiring on level 8 of Forest A
- Install gurneyway connection on level 9 of Forest A
All work will take place 8-6pm weekdays and 9-6pm on Saturdays.