The 310,000 square-foot addition will add an eight-story building and will includes diagnostic and treatment facilities, primarily out-patient cancer and others) labs, new state-of-the-art operating rooms, 20 inpatient beds, and a lobby. There will be two floors of underground parking and sterile processing. This will bring SCH bed total to 409, up from 200 before its expansion 2012 plan.
The helicopter landing pad moved temporarily to the roof of Forest A (176’), now known as Friends of Costco Building, Phase 1 of the expansion. The landing pad will be active until Building Care is completed. Noise is expected to be louder than the former ground-based helipad. When Forest B is complete, the helistop will moves to its permanent location on top of the Friends of Costco Building (same height).
Lights were added to the horizontal swing arm (boom) portion of the tower crane to increase safety for helicopter landings. These are in addition to the lights at the end of the boom and on the crane operator’s cab. The additional lights will help the helicopter pilots in identifying the location of the boom when landing or departing the helipad in the dark. While the lights are visible from the ground, they are not bright enough to interfere with any neighboring properties. As a reminder, the tower crane is scheduled to remain onsite through August 2020.
The Hospital posted this information on their Construction Blog about specific construction activity this week:
- Pour concrete for pads, walls, shafts, and landings
- Install fireproofing
- Framing
- Paint
- Install roofing
- Set walls
- Install windows
- Install metal sheeting
- Install elevator equipment
- Install mechanical and electrical wiring and plumbing equipment
- Install drywall
- Install siding
- Build out electrical, mechanical, generator and pneumatic tube blower rooms
- Install insulation
- Install flooring
- Install sprinkler systems
- Build out interior spaces
- Electrical power installation (Seattle City Light)
- Work in existing buildings:
- Set up Starbucks kiosk on River B level 3
- Install wall coverings, clean, and remove infection prevention barriers in new chapel location on River A level 7
- Building connection work:
- Complete framing and install seismic joints and utility wiring on level L1 of Forest A
- Frame walls, saw cut wall, and install fireproofing and steel on level 1 of Forest A
- Set walls on level 4 of Forest A
- Set walls on level 5 of Forest A
- Install seismic joints and utility connections on level 6 of Forest A
- Complete framing and install utility wiring and seismic joints on level 7 of Forest A
- Install seismic joint covers on level 8 of Forest A
All work will take place 8-6pm weekdays and 9-6pm on Saturdays.
No comments:
Post a Comment