This Week Hospital Construction Work



Hospital Construction Activity This Week



 












Building Care, also called Forest B, of Phase 2 of Children's Hospital expansion is underway and the new building is planned to open in Spring of 2022. 
The 310,000 square-foot addition will add an eight-story building and will includes diagnostic and treatment facilities, primarily out-patient cancer and others) labs, new state-of-the-art operating rooms, 20 inpatient beds, and a lobby. There will be two floors of underground parking and sterile processing. This will bring SCH bed total to 409, up from 200 before its expansion 2012 plan. 

The helicopter landing pad moved temporarily to the roof of Forest A (176’), now known as Friends of Costco Building, Phase 1 of the expansion. The landing pad will be active until Building Care is completed. Noise is expected to be louder than the former ground-based helipad. When Forest B is complete, the helistop will moves to its permanent location on top of the Friends of Costco Building (same height). 
Lights were added, recently, to the horizontal swing arm (boom) portion of the tower crane to increase safety for helicopter landings. These are in addition to the lights at the end of the boom and on the crane operator’s cab. The additional lights will help the helicopter pilots in identifying the location of the boom when landing or departing the helipad in the dark. While the lights are visible from the ground, they are not bright enough to interfere with any neighboring properties. As a reminder, the tower crane is scheduled to remain onsite through August 2020.

The Hospital posted this information on their Construction Blog about specific construction activity this week: 
  • Erect structural and support steel
  • Install decking
  • Install waterproofing
  • Pour concrete for walls, shafts, slabs, decks and stairs
  • Paint
  • Base framing for connection to River
  • Install anchors for windows
  • Set and weld exterior walls
  • Set up lift system
  • Install glass
  • Set stairs
  • Install elevator machines and equipment
  • Install mechanical, electrical and plumbing equipment
  • Build out electrical, mechanical and pneumatic tube blower rooms
  • Install drywall
  • Load in and set air handling units
  • Install fire sprinkler systems
  • Install flooring
  • Demolition for connection points to Forest A
  • Interior activities: install mechanical, electrical, plumbing and drywall in River B patient family lounge; install infection prevention barriers and conduct demolition on lower level 1 of Forest A for building connection
  • Work to repair a broken storm water pipe at the north end of the hospital campus, near NE 50th Street. This work will require the removal of some trees. Noise from excavators, chainsaws and wood chippers will be generated between 8 a.m. and 6 p.m. on those days. Please contact Meghan Fuller, manager of Grounds Maintenance, at 206-307-6687 if you have questions.

Work hours are 8-6pm weekdays and 9-6pm on Saturday. 