Monday, December 16, 2019

Children's Hospital Construction Activity This Week














Building Care, Forest B, of Phase 2 of Children's Hospital expansion,Children's Hospital is underway, which is planned to open in Spring of 2022. 

The 310,000 square-foot addition will add an eight-story building and will includes diagnostic and treatment facilities, primarily out-patient cancer and others) labs, new state-of-the-art operating rooms, 20 inpatient beds, and a lobby. There will be two floors of underground parking and sterile processing. This will bring SCH bed total to 409, up from 200 before its expansion 2012 plan. 

The helicopter landing pad moved temporarily to the roof of Forest A (176’), now known as Friends of Costco Building, Phase 1 of the expansion. The landing pad will be active until Building Care is completed. Noise is expected to be louder than the former ground-based helipad. When Forest B is complete, the helistop will moves to its permanent location on top of the Friends of Costco Building (same height). 

Lights were added, recently, to the horizontal swing arm (boom) portion of the tower crane to increase safety for helicopter landings. These are in addition to the lights at the end of the boom and on the crane operator’s cab. The additional lights will help the helicopter pilots in identifying the location of the boom when landing or departing the helipad in the dark. While the lights are visible from the ground, they are not bright enough to interfere with any neighboring properties. As a reminder, the tower crane is scheduled to remain onsite through August 2020.

The Hospital posted this information on their Construction Blog about specific construction activity this week: 

  • Install rebar and pour concrete for walls, slabs, vestibule, sidewalk, and curbs
  • Install overhead protection measures
  • Install support steel
  • Erect structural steel - will be the loudest activities
  • Install waterproofing on walls
  • Install infection prevention barrier
  • Set stairs
  • Install elevator machines
  • Install fire sprinkler system
  • Install sewer, storm and water pipes
  • Install underground natural gas sleeves near 40th Avenue NE
  • Internal activities: install new pipe, wiring and pneumatic tube system pathways on Forest A, level 1; install pipes for pneumatic tube system extension; reconfigure equipment in existing fire command center

Call 206-987-8000 or email construction@seattlechildrens.org with questions.