Hospital Construction Activity This Week












Building Care, also called Forest B, of Phase 2 of Children's Hospital expansion is underway and the new building is planned to open in Spring of 2022.

The 310,000 square-foot addition will add an eight-story building and will includes diagnostic and treatment facilities, primarily out-patient cancer and others) labs, new state-of-the-art operating rooms, 20 inpatient beds, and a lobby. There will be two floors of underground parking and sterile processing. This will bring SCH bed total to 409, up from 200 before its expansion 2012 plan.

The helicopter landing pad moved temporarily to the roof of Forest A (176’), now known as Friends of Costco Building, Phase 1 of the expansion. The landing pad will be active until Building Care is completed. Noise is expected to be louder than the former ground-based helipad. When Forest B is complete, the helistop will moves to its permanent location on top of the Friends of Costco Building (same height).
Lights were added to the horizontal swing arm (boom) portion of the tower crane to increase safety for helicopter landings. These are in addition to the lights at the end of the boom and on the crane operator’s cab. The additional lights will help the helicopter pilots in identifying the location of the boom when landing or departing the helipad in the dark. While the lights are visible from the ground, they are not bright enough to interfere with any neighboring properties. As a reminder, the tower crane is scheduled to remain onsite through August 2020.

The Hospital posted this information on their Construction Blog about specific construction activity this week:

  • Pour concrete for walls and shafts
  • Install fireproofing
  • Framing
  • Paint
  • Install roofing
  • Install windows
  • Install metal sheeting
  • Install elevator equipment
  • Install mechanical and electrical wiring and plumbing equipment
  • Set air handling units
  • Install drywall
  • Install siding
  • Build out electrical, mechanical, generator and pneumatic tube blower rooms
  • Install pneumatic tube stations
  • Core drilling
  • Install insulation
  • Install flooring
  • Install sprinkler systems
  • Build out interior spaces
  • Work in existing buildings:
    • Install utility wiring and pipes, install ceiling grid, and paint on River B level 3 in old vending machine location for Starbucks coffee cart
    • Install paneling, doors, and windows in new chapel location on River A level 7
  • Building connection work:
    • Set up infection prevention barriers and begin demolition on level 1 of Forest A
    • Demolition and set walls on level 2 of Forest A
    • Install steel and set walls on level 3 of Forest A
    • Install seismic joints and connections for mechanical, electrical, plumbing, and pneumatic tube system on level 4 of Forest A
    • Complete framing and install connections for mechanical, electrical, plumbing, and pneumatic tube system on level 5 of Forest A
    • Complete framing and install connections for mechanical, electrical, and plumbing on level 6 of Forest A
    • Complete framing and install connections for mechanical, electrical, and plumbing on level 7 of Forest A
    • Install utility wiring, insulation, and drywall on level 8 of Forest A
    • Install utility wiring and waterproofing on level 9 of Forest A

All work will take place 8-6pm weekdays and 9-6pm on Saturdays.