• Erect structural and support steel
  • Install decking
  • Pour concrete for walls, shafts, curbs, slabs, decks and stairs
  • Install fireproofing
  • Install anchors for windows
  • Set and weld walls
  • Install glass
  • Set stairs
  • Install mechanical, electrical and plumbing equipment
  • Install elevator machines
  • Paint
  • Seal floors
  • Install fire sprinkler systems
  • Install rain leaders
  • Demolition at Forest A level L1 connection point
  • Install fuel oil pipes
  • Internal activities: install pipes for pneumatic tube system extension in River building; set up infection prevention barriers at Forest A connection points and River B family lounge
The loudest activities will be those associated with erecting the steel and the demolition at the Forest A level L1 connection point. Expect heavy truck traffic, primarily for concrete and steel delivery. 
Work hours are 8-6pm weekdays and 9-6pm on Saturday. 
For questions, call 206-987-8000 or email construction@seattlechildrens.org